When Forest Restoration Collides With Endangered Species Protection
A federal judge set aside approval of an oak-hickory restoration project in Shawnee National Forest after the Forest Service made its decision before completing consultation over endangered Indiana bats. The harder question is not whether logging is good or bad. It is how agencies should handle competing ecological risks.
The court did not rule that forest restoration was wrong.
The U.S. Forest Service approved the roughly 67-acre McCormick Oak-Hickory Restoration Project on October 7, 2024, after determining that endangered Indiana bats were likely to be adversely affected. But formal Endangered Species Act consultation with the U.S. Fish and Wildlife Service was still underway.
The final biological opinion arrived November 19, more than a month after the approval. A federal judge has now ruled that the consultation was supposed to inform the agency’s decision—not follow it. [1]
That leaves a more useful question than “logging versus conservation”: what should happen when an action intended to improve one part of an ecosystem may create risk for another?
On paper, both sides of this project were about conservation.
The McCormick Oak-Hickory Restoration Project was not proposed simply to produce timber.
The Forest Service described the work as an intermediate thinning project intended to reduce overcrowding in a section of Shawnee National Forest in Pope County. By removing selected hardwood trees, managers hoped to open portions of the canopy, reduce competition for water and nutrients, and maintain oak-hickory forest conditions. [1] [3]
That objective fits a much larger management problem in southern Illinois. Oak-hickory forests developed under disturbance conditions that are difficult to reproduce in modern forests. Without intervention, shade-tolerant species can gradually replace oak in some stands. Shawnee National Forest planning documents explicitly recognize thinning, prescribed fire, and other disturbance as tools for maintaining oak-hickory systems. [4]
But the same trees being evaluated for removal can also function as wildlife habitat.
In this case, that included potential summer habitat for the federally endangered Indiana bat.
Oak-Hickory Restoration
Reduce stand overcrowding, create canopy openings, direct resources toward remaining trees, and maintain oak-hickory conditions over time.
Indiana Bat Protection
Reduce the chance that occupied summer roost trees are removed while bats are present and ensure federally required species consultation informs the project.
The sequence of events became the legal problem.
The central issue was not simply what the agencies concluded about the Indiana bat. It was when those conclusions became part of the decision.
McCormick Project Timeline
2024
The agency signs its Decision Memo authorizing the approximately 67-acre oak-hickory thinning project.
2024
The U.S. Fish & Wildlife Service completes formal consultation concerning Indiana bats and other listed species.
2025
Work starts during the summer. Roughly 40 acres are treated before litigation temporarily stops operations.
2025
The court temporarily stops implementation of the commercial timber harvest.
2025
The court rejects the plaintiffs’ request for a longer injunction based on their then-existing NEPA arguments. The contractor nevertheless does not return.
2026
The court finds that Endangered Species Act consultation should have been completed before the Forest Service made its final decision.
That final ruling vacated the 2024 Decision Memo and returned the project to the Forest Service. [1]
Why would forest restoration involve cutting trees?
That question is central to understanding the dispute.
Forests are not automatically healthier simply because they contain more trees. In an overstocked stand, too many trees can compete for limited growing space, water, nutrients, and light. The Forest Service said those conditions were reducing resilience to drought, insects, and disease in the McCormick project area. [2]
Selective thinning is one method foresters use to change those conditions. Removing some trees can create canopy gaps, reduce competition, and provide additional sunlight for oak regeneration.
Shawnee’s broader forest plan describes active disturbance as part of maintaining oak-hickory forest and preventing a continued shift toward more shade-tolerant forest types. [4]
This was not simply a timber-production argument.
Commercial timber removal was the method used to carry out the treatment, but the agency’s stated objective was forest health, resilience, and maintenance of oak-hickory conditions.
That distinction does not automatically make the project ecologically correct. It does mean the project should be judged as a management intervention rather than reduced to a simple “trees cut versus trees protected” argument.
The Indiana bat made the timing of tree removal matter.
The Indiana bat (Myotis sodalis) has been federally protected for decades and remains listed as endangered.
During winter, Indiana bats concentrate in caves and mines. During the warmer part of the year, forests become critical habitat. Reproductive females form maternity colonies, and summer roosts are commonly located beneath loose or peeling bark on large living or dead trees. [5]
They also forage through forested habitat, along edges, and around riparian areas.
Surveys in the McCormick project area detected acoustic calls attributed to Indiana bats and tri-colored bats. Follow-up mist-net surveys did not capture either species, and investigators did not identify evidence of an Indiana bat maternity colony in the project area. [2]
But the Forest Service’s own biological assessment concluded that Indiana bats were likely to be adversely affected by the project because an individual bat could be injured or killed if an occupied roost tree were cut. [1]
That did not mean the project necessarily threatened the species as a whole. It meant that formal consultation under the Endangered Species Act had become part of the required decision process.
The biological opinion was supposed to inform the decision.
Once a federal agency determines that a proposed action may adversely affect a listed species, Section 7 of the Endangered Species Act requires formal consultation with the U.S. Fish & Wildlife Service.
That consultation results in a biological opinion evaluating the project’s effects and whether the action is likely to jeopardize a listed species.
Determine whether the proposed federal action may affect a protected species.
Fish & Wildlife Service provides its biological opinion and applicable conservation measures.
The action agency decides whether and how to proceed using the completed consultation.
The Forest Service recognized that Indiana bats were likely to be adversely affected.
The Decision Memo was signed October 7, 2024.
Formal consultation was completed November 19, after the project decision had already been made.
The Forest Service argued that the timing caused no meaningful harm. The timber sale was not advertised until after the biological opinion had been issued, and the agency maintained that the final document contained little information it did not already know.
Judge Nancy J. Rosenstengel rejected that argument.
The court concluded that consultation is supposed to occur before final agency action so that the biological opinion can influence whether—and in what manner—the agency proceeds. [1]
What This Really Means
The ruling is not a court choosing bats over forests.
It is a court saying that an agency cannot decide how to balance those ecological interests first and finish the federally required endangered-species review afterward.
The difference was more than six weeks of paperwork.
The final biological opinion focused attention on one practical risk: cutting potential roost trees while Indiana bats could be using them.
The court discussed existing forest-plan protections restricting removal of potential roost trees between April 1 and September 30, subject to specified exceptions. [1]
Why the season of tree removal matters
This graphic explains the seasonal provision discussed in the court record. It is not a claim that every tree contains a bat or that all forest work is prohibited during the active season. Project-specific requirements and exceptions still matter.
The McCormick project did not impose a blanket requirement that the contractor wait until the inactive season to conduct the commercial harvest.
Logging began in August 2025.
That turned the difference between the earlier Forest Service analysis and the later biological opinion into something the court could not dismiss as harmless.
The Forest Service might still have approved the same treatment after reviewing the biological opinion. It might have imposed different timing restrictions or modified how the remaining work would occur.
The point is that the agency was supposed to make that choice after consultation was complete.
By the time the dispute reached court, much of the work was already done.
Commercial thinning began in August 2025 and continued for roughly eight days before the court issued a temporary restraining order.
Approximately 40 of the project’s 67 acres had been treated by that point. [1] [6]
The temporary order did not become a long-term injunction. On September 11, 2025, the court rejected the plaintiffs’ request for a preliminary injunction after determining that they had not shown a sufficient likelihood of success on their original NEPA claim. [2]
The contractor was then legally able to resume work.
It did not.
The project remained dormant while the litigation continued, and the plaintiffs later added the Endangered Species Act issue that ultimately succeeded.
That earlier ruling matters.
The same court that ultimately set aside the project had previously declined to halt it under the plaintiffs’ initial NEPA arguments.
That is one reason this should not be reported as a judge simply deciding that the Forest Service’s ecological reasoning was invalid. The successful claim concerned a specific failure in the Endangered Species Act consultation process.
What the judge did—and did not—decide.
✓ The Court Did Decide
- The Forest Service completed required ESA consultation too late in the decision process.
- The October 2024 project approval had to be set aside.
- The project must return to the Forest Service for reconsideration.
— The Court Did Not Decide
- That oak-hickory thinning is inherently harmful.
- That the project would jeopardize the Indiana bat species.
- That the remaining work can never be approved.
- The merits of every remaining NEPA argument.
The court granted summary judgment on the Endangered Species Act issue, vacated the Forest Service’s decision, and remanded the matter to the agency. [1]
That leaves the Forest Service free to reconsider the project using the completed consultation and determine what should happen next.
Restoration projects can create their own ecological risks.
That sounds contradictory only if restoration is treated as a synonym for “good.”
Restoration is an objective. The actions used to reach that objective still have effects.
A manager may thin trees to improve oak regeneration while temporarily reducing roosting opportunities for a forest bat. Prescribed fire may improve a fire-dependent plant community while creating short-term disturbance for another species. Removing invasive vegetation may benefit native plants while temporarily altering cover used by wildlife.
Those conflicts do not mean managers should stop managing.
They mean the ecological goal of a project cannot substitute for evaluating what the project actually does.
That distinction connects directly with adaptive management . A defensible management system has to identify objectives, evaluate risk, monitor results, and remain capable of changing course when evidence changes.
In the Shawnee case, federal law added another requirement: endangered-species consultation needed to be part of that decision before the agency committed to the action.
The harder question is how agencies choose between ecological risks.
A simple political framing would put the Forest Service on one side, environmental groups on the other, and label the dispute “logging versus conservation.”
That misses what makes the case useful.
The Forest Service had an ecological argument for intervention. Oak-hickory systems can require disturbance and active management to maintain the conditions managers are trying to conserve.
The Indiana bat also presented a legitimate ecological concern, backed by federal protection and the possibility that individual bats could occupy trees selected for removal.
Those facts can both be true.
Doing nothing changes a forest.
Thinning changes it too.
The real work of public-land management is deciding which change is acceptable, how much risk is justified, when an action should occur, what evidence supports it, and how the decision will change if new information points somewhere else.
That is why this case belongs as much in Policy & Management as it does in Wildlife .
The ruling stops the old approval. It does not necessarily end the project.
The October 2024 Decision Memo can no longer support the unfinished work.
But the Forest Service can return to the project, reconsider it using the completed biological opinion, and make another decision.
That could lead to stronger seasonal restrictions. It could change how the remaining acres are treated. Or the agency could conclude, after completing the required process, that essentially the same management action remains appropriate. [1]
The next decision may tell us more about this case than the court ruling alone.
The question now returns to the forest.
Can the remaining oak-hickory restoration work be completed in a way that reduces risk to Indiana bats while still accomplishing the Forest Service’s management objective?
That is not a question that can be answered by calling the project either “logging” or “restoration.” It requires managers to explain the tradeoff, the evidence, and the safeguards they choose.
Key Takeaways
- The McCormick project had a restoration objective. The Forest Service proposed selective commercial thinning to reduce overcrowding and maintain oak-hickory conditions.
- Indiana bats complicated the treatment. Forest trees can function as summer roost habitat, and the Forest Service determined the species was likely to be adversely affected.
- The legal failure was about sequence. The project was approved October 7, 2024; the final biological opinion was not completed until November 19.
- The court did not permanently prohibit the project. It vacated the existing approval and returned the issue to the Forest Service.
- The broader lesson reaches beyond Shawnee. Restoration projects still require managers to identify and account for ecological tradeoffs rather than assuming a beneficial objective guarantees a beneficial outcome.
Frequently Asked Questions
Did the judge permanently ban logging in this part of Shawnee National Forest?
No. The court set aside the existing project approval and returned the matter to the Forest Service. The agency may reconsider the project and could potentially approve additional work after properly completing the required decision process.
Did the court find that the project would kill Indiana bats?
No. The Forest Service acknowledged a risk that an individual bat could be injured or killed if an occupied roost tree were removed, but the court did not rule that the project would jeopardize the Indiana bat as a species.
Were Indiana bats found in the project area?
Acoustic surveys detected calls attributed to Indiana bats. Follow-up mist-net surveys did not capture Indiana bats, and investigators did not identify evidence of a maternity colony within the project area.
Why does the time of year matter?
Indiana bats use forest trees for summer roosting. The court record discusses restrictions on cutting potential roost trees between April 1 and September 30, when bats may be using forest habitat.
Did the judge rule that the Forest Service violated NEPA?
The August 2026 ruling resolved the case through the Endangered Species Act issue without deciding the remaining NEPA claims. The court had previously denied a preliminary injunction based on the plaintiffs’ earlier NEPA arguments.
References & Further Reading
- U.S. District Court for the Southern District of Illinois. Friends of Bell Smith Springs et al. v. United States Forest Service et al. Memorandum and Order, August 31, 2026. Case No. 3:25-CV-01377-NJR. Read the court order .
- U.S. District Court for the Southern District of Illinois. Memorandum and Order denying preliminary injunction, September 11, 2025. Read the order .
- U.S. Forest Service. Shawnee National Forest Schedule of Proposed Actions. McCormick Oak-Hickory Restoration Project, Project 66483. The Forest Service described the project as intermediate hardwood thinning intended to promote ecosystem health, resilience, and maintenance of oak-hickory stands. View Forest Service record .
- U.S. Forest Service. Shawnee National Forest, 2006 Forest Plan Record of Decision. The plan discusses disturbance and vegetation management as tools for maintaining oak-hickory forest conditions. View Forest Plan material .
- U.S. Fish & Wildlife Service. Indiana Bat (Myotis sodalis) species profile. Habitat, conservation status, summer roosting, and life-history information. View species profile .
- WKMS. Will Darnall. “Federal judge orders commercial logging project in Shawnee National Forest to halt operations.” September 3, 2026. Read regional coverage .
